Northcot Brick Shut Down Project
A busy Christmas and New Years at Northcot Brick for their annual shut down. We only had a small window and lots to complete, but nothing we have not done before.
- We built and installed the Gas safety Solenoid panel on the main kiln.
- We installed soft starters on both 75kw and 45kw motors on the high speed rolls.
- Rewired and reprogrammed the alarm panels for the dryers.